Our Business

Contract No. KWSP2/W-3-2 of Construction of Primary/Secondary/Tertiary Distribution Network, Service Connection and Water Supply to Low Income Communities: Western Parts of Karnaphuli Service Area under Karnaphuli Water Supply Project - Phase 2 (KWSP2) – construction of distribution pipelines with 8.3km of DN300 to DN1000 DI pipes, 242km of dia.75mm to dia.250mm HDPE pipes, 18,105 water service connections and 7.3km of optic fibre cables.

*****The Employer: CWASA

*****Financed by: JICA

*****Contract award date: October 19, 2016

*****Contract amount: BDT3,232,490,650 + JPY1,047,471,351 (total approximately

equivalent to USD 50.19 million)

*****Time for completion: 4.5 years