Our Business

Construction of Clear Water Transmission Mains including River Crossing, KWSP -- Construction of clear water transmission mains and partial distribution pipe network from newly built water treatment plant outside the Khulna city urban area to 7 reservoirs in the city urban area, total length of pipeline is 57 km, of which 40.8 km of ductile iron pipes (diameter DN300mm to DN1200mm) and 16.2km of HDPE pipes (diameter OD75mm-OD250mm). In addition approximate 700m of DN1000mm steel pipes need for river crossing by HDD method.

*****The Employer: KWASA

*****Financed by: Asian Development Bank(ADB)

*****Contract award date: June 2, 2014

*****Contract signing data: June 9, 2014

*****Contract amount: BDT 2,203,222,309.00 (approximately equivalent to USD

28.34 million)

*****Time for completion: 780 days

*****Commencement date: November 27, 2014